Energy-aware planning of continuous casting and hot rolling considering steel grade upgrades

Gärtner, Nico, Schulz, Christopher, Volling, Thomas
OR Spectrum · Springer Nature · 2026-09-30 · DOI: 10.1007/s00291-026-00877-8

Abstract

Continuous casting (CC) and hot rolling (HR) are the key processes in steel production for turning liquid steel into solidified coils with order-specific properties and dimensions. Due to different process restrictions, planning and scheduling of both processes is traditionally completely separated. As a result, the intermediate products after CC, so-called slabs, are stored temporarily for further processing, where they cool down considerably. However, for HR slabs have to be reheated to a process temperature of approximately $$1,200^\circ $$ C, making the CC-HR interface one of the most energy-intensive stages in steel production. Integrated CC-HR planning could help minimize slab waiting times and maximize energy efficiency. To address this issue, we formulate a mixed-integer non-linear program (MINLP) that utilizes flexibility stemming from steel grade upgrades to improve coordination. We investigate the potential of integrated CC-HR planning and its dependence on upgrade flexibility and product variety through a numerical study. Problem instances with increasing planning horizons are considered to assess scalability. As larger instances cannot be solved by an exact solver within practical time limits, a GRASP-based heuristic enhanced by a local branching improvement phase is employed. The findings indicate considerable improvement potential at the CC-HR interface, with most benefits attainable under moderate flexibility. These effects remain stable across different planning horizons.

Read at publisher →

Similar articles